It's Always Easy with

eZaccessbathroomS.com

HOME     Grab Bars, Doors, and More     Handicap Bathrooms     Classic Bathrooms     Tub to Shower Conversions     Kitchens and Floors     Testimonials     About Us     CONTACT US      
handicap explained
privacy policy
HOW TO
Do-It-Yourselves
Free Advice
DIYers. Now a service to help you out. Expert advice and on-site supervison of your progress and/or your sub-contractors. All these proceedures and much, much more.
Service charge and hourly rates.
PROTILE
eZaccessbathroomS.com
832.202.8453
762 Arvana

Houston ,Texas 77034

(832) 202-TILE  (8453)
762 Arvana
Houston ,Texas 77034
PROTILE'S EXCLUSIVE PROCEDURE LISTS
P1SETTING UP PROCESS (FLOORS)
P2SETTING UP PROCESS (FURNITURE)
P3SETTING UP PROCESS (EXTERIORS)
P4DOOR REMOVAL
P5PREPARING THE BATHROOM
P6COMMODE REMOVAL
P7VANITY /CT/LAVA. FAUCET REMOVAL
P8DECONSTRUCTING SHOWER
P9SHOWERDRAIN INSTALLATION / CONCRETE
P10WOOD RECONSTRUCTION
P11FAUCET INSTALLATION
P12SHOWERPAN 40 MIL INSTALLATION
P13LIGHT/HEATER/VENT INSTALLATION
P14SHEETROCK INSTALLATION
P15HARDI-BOARD/DUROCK
P16MUD SETTING THE TOP & INSIDE OF CURB
P17SHOWERBENCH CONSTRUCTION
P18SET-UP FOR SHOWER TILE INSTALLATION
P19WET SAW 
P20GROUTING & FINISH PLUMBING SHOWER
P21MUDPACKING SHOWERPAN
P22GROUT SHOWER FLOOR
P23SLIDING SHOWER DOOR INSTALLATION
P24RESTROOM FLOOR TILE INSTALLATION
P25VANITY INSTALLATION
P26R & R MEDICINE CABINET INSTALLATION
P27LAVATORY, FAUCET,& DRAIN INSTALLATION
P28COMMODE INSTALLATION
P29GROUTING RR FLOOR
P30WRAP UP PHASE
P31DECONSTRUCTING TUB-TOP
P32TUB REMOVAL
P33DECONSTRUCTING TT & WAIN COATING
P34SET-UP FOR TILE INSTALLATION
P35GROUTING & FINISH PLUMBING TUB-TOP
P36TAPE& FLOATING HARDI BACKER JOINTS
P37FLOOR TILE INSTALLATION
P38TUB INSTALLATION
P39DECONSTRUCTING FIBERGLASS 
P40GROUTING FLOOR
P41LAVA. & FAUCET REMOVAL
P42LAVATORY, FAUCET, DRAIN INSTALLATION
P43PAINTING
P44SETTING UP PHASES
P45TUB TO SHOWER DRAIN CONVERSION
P46SHOWER DOOR PIVOT TYPE INSTALLATION
P47THINGS TO DO
P48ZEE BAR INSTALLATION
P49SHOWERDRAIN INSTALLATION ON PAN
P50MOLDING D&R OR REPLACEMENT
P51GRAB BAR INSTALLATION
P52ANGLE STOP REPLACEMENTS
P53CLOSET FLANGE REPLACEMENT
P54GLASS BLOCK INSTALLATION ON WINDOW OPENING
P101DOOR ENLARGEMENT
P102 WALLPAPER REMOVAL
P103 HEATER LIGHT EXHAUSTFAN INSTALLATION
P1SETTING UP PROCESS (FLOORS)
SETTING UP THE JOB SITE
THIS PART OF THE JOB IS TO INSURE THAT NOTHING THAT BELONGS TO THE
HOMEOWNER WILL BE DAMAGED WHILE WE ARE THERE FULL-FILLING OUR OBLIGATIONS
TOOLS NEEDED  :
BLADE, SCISSORS, MEASURING TAPE, 
WEIGHTS TO HOLD DOWN PAPER
MATERIALS NEEDED  :
CONTRACTORS PAPER, PAINTER'S TARPS, CANVASSES, 
BLUE PAINTER'S MASKING TAPE, STANDARD MASKING TAPE, AND TRANSPARENT TAPE
PROCEDURE  :
RELOCATE ANY AND ALL ITEMS OF FURNISHING THAT MAY BE IN THE WAY OF
WHERE WE WILL BE WORKING AT AND THROUGH.
LAY OUT THE PAPER AND TAPE IT DOWN WITH MASKING TAPE AS YOU GO ALONG
LAY OUT THE PAPER IN AS STRAIGHT LINE AS POSSIBLE AS TO NOT TRIP
WHILE WE ARE WORKING
START THE LAYOUT FROM THE WORK SITE TO THE FRONT DOOR
ALSO LAY SOME PAPER DOWN OUT OF THE WAY TO SIT THE TOOL BOXES 
WHILE THEY ARE IN USE FOR THE DURATION OF THIS REMODELING PROJECT
LAY DOWN THE PAINTER'S TARPS WHERE WE WILL BE WALKING ON THE CARPET
P2SETTING UP PROCESS (FURNITURE)
TOOLS NEEDED  :
BLADE, SCISSORS, MEASURING TAPE, 
MATERIALS NEEDED  :
PAINTER'S PLASTIC TARPS, 
PROCEDURE  :
MEASURE ALL THE FURNISHING THAT WILL BE PROTECTED
CUT THE TARPS AND OPEN THEM UP
COVER THE FURNITURE AND TAPE THE PLASTICS TO THE FURNITURE
MAKE SURE THAT THE TARPS REACH ALL AROUND AND TO THE FLOOR
P3SETTING UP PROCESS (EXTERIORS)
TOOLS NEEDED  :
MATERIALS NEEDED  :
16' X 20' BLUE TARP
SCRAP TO WEIGHT DOWN THE TARP TO PREVENT IT FROM MOVING
PROCEDURE  :
UNFOLD THE TARP AND LAY IT ACROSS THE DRIVEWAY. WEIGHT IT DOWN WITH
ITEMS HEAVY ENOUGH TO HOLD IT IN PLACE
CONTINUE BY OFF LOADING THE TOOL BOXES AND LAYING THEM ON THE TARP
P4DOOR REMOVAL
TOOLS NEEDED:
PUTTY KNIFE , HAMMER , RYOBI SCREWGUN, SCREWDRIVER
MATERIALS:
MASKING TAPE, SHARPIE MARKER, 
PROCEDURE
BANG OUT THE DOOR PINS WITH THE PUTTY KNIFE
IF THEY DO NOT COME OUT
USE THE SCREWGUN TO DISASSEMBLE THE HINGE
TAPE THE SCREWS AND HARDWARE TO THE TOP OF THE DOOR
STORE THE DOOR OUT OF THE WAY
P5PREPARING THE BATHROOM
TOOLS NEEDED  :
LOADED POUCH , SCREW GUN , STRING , THREE WAY EXTENSION CORD  
WINDOW EXHAUST FAN , RYOBI SCREWGUN , STANDARD EXTENSION CORD
MATERIALS NEEDED  :
1 5/8" DRYWALL SCREWS, 
PROCEDURE  :
REMOVE ALL THE TOILETRIES AND SET THEM ASIDE. REMOVE ALL HARDWARE . 
INSTALL THE EXHAUST FAN  ON THE WINDOW SILL AND SECURE
SET UP THE TOOLS AND BUCKETS
P6COMMODE REMOVAL
TOOLS NEEDED  :
VACCUME CLEANER ,, SMALL CHANNEL LOCKS , SMALL CRESCENT WRENCH
BLUE-WAY SCREWDRIVER
LATEX GLOVES , COMMODE PUTTY KNIFE ,  NEWS PAPER , BUCKET FOR TRASH
(POSSIBLE GRINDER, EAR PLUGS, SAFETY GLASSES, HANKERCHEIF )
MATERIALS NEEDED  :
PROCEDURE  :
TURN OFF WATER SUPPLY
LAY FLOOR PROTECTION WHERE COMMODE WILL BE STORED
CONNECT THE VACCUME CLEANER W/WATER
REMOVE AND STORE THE COMMODE LID IN A SAFE PLACE
REMOVE THE WATER FROM THE COMMODE BOWL AND TANK
REMOVE 7/16" NUTS AND  CLOSET BOLTS
DISCONNECT WATER SUPPLY LINE
REMOVE COMMODE & SET IT OUT OF THE WAY
CLEAN OFF WAX FROM COMMODE BOTTOM
CLEAN OFF CLOSET FLANGE WITH PUTTY KNIFE
CLEAN OFF PUTTY KNIFE WITH NEWSPAPER
STUFF NEWSPAPER OVER CLOSET FLANGE
SECURE PROTECTION OVER CLOSET FLANGE
TAKE VACCUME CLEANER OUT EMPTY ,  CLEAN ,  AND STORE AWAY
P7VANITY /CT/LAVA. FAUCET REMOVAL
TOOLS NEEDED  :
LARGE AND SMALL  CHANNEL LOCKS ,  SMALL CRESCENT WRENCH
SMALL GROUT BUCKET FOR WATER AND SPONGE
BASIN WRENCH , RYOBI LIGHT
PROCEDURE
TURN OFF THE ANGLE STOPS
DISCONNECT 1 1/4" PVC OR BRASS PETE-TRAP LAVATORY DRAIN LINE
DISCONNECT SUPPLY LINES TO FAUCET
REMOVE COUNTER TOP END CAPS 
REMOVE COUNTER TOP  
REMOVE SCREW THAT ATTACH VANITY TO WALL 
REMOVE VANITY
DISCARD ALL ITEMS THAT ARE NOT TO BE REUSED
P8DECONSTRUCTING SHOWER
THE REASON WE CALL IT DECONSTRUCTION IS BECAUSE WE TAKE EXTRA CARE
NOT TO CAUSE ANY LATERAL DAMAGE TO THE WORK AREA.
TOOLS NEEDED  :
PRIMARY AND SECONDARY TOOL BOXES , PRY BARS  ,  ZAW-ZALL 
THREE WAY EXTENSION CORD , EMPTY BUCKETS , BROOM ,  DUST PAN , SHOVEL
MASK , GOGGLES , GLOVES ,  EAR PLUGS , 5 LB HAMMER , PALITA ,  RYOBI 
POWER SCRAPER, FOUR WAY SCREWDRIVER ,  ALL LEVELS , PENCILS 
EXHAUST WINDOW FAN
MATERIALS NEEDED  :
PROCEDURE  :
SET UP WORK AREA, START BY REMOVING THE SHOWER DRAIN STRAINER, PLUG
UP THE DRAIN TO PREVENT DEBRIS FROM ENTERING THE DRAIN LINE , 
INSTALL THE EXHAUST WINDOW FAN WITH EXTENSION CORD. REMOVE
THE SHOWER FLOOR WITH THE POWER SCRAPER , REMOVE ALL THE TRASH, 
TAKE OF ALL THE CAPS, CUT OUT THE WALL WITH THE ZAW-ZALL, PRY  THE WALLS
AWAY FROM THE 2X4S, REMOVE THE WALLS, CLEAN UP THE SHOWER WALLS OF
NAILS AND LEFTOVER SHOWER PAN MATERIAL,
P9SHOWERDRAIN INSTALLATION / CONCRETE
TOOLS NEEDED 
PRIMARY, SECONDARY, & PLUMBING TOOL BOXES , ZAW-ZALL, HAMMER DRILL 
THREE WAY EXTENSION CORD , EMPTY BUCKETS , BROOM , DUST PAN 
MASK GOGGLES , GLOVES ,  EAR PLUGS  , PALITA , RYOBI , POUCH
INSIDE TUBE CUTTER, TORPEDO LEVEL, MAKITA POWER SCRAPER
MATERIALS NEEDED
 2" PVC DRAIN WITH/WITHOUT  GASKET ?????  
PVC PRIMER AND GLUE, MASKING TAPE, 
2"PVC PIPE , 3  2 " COUPLINGS, 1 1/2" TO 2" REDUCER
NO HUB COUPLING 1 1/2" TO 2"
2" PVC PETE TRAP
PROCEDURE
SET UP WORK AREA, START BY REMOVING THE SHOWER DRAIN, DIG INTO THE
FOUNDATION AS NEEDED TO REMOVE THE DRAIN OR TO GET ACCESS TO THE DRAIN
LINE, PREPARE THE DRAIN LINE FOR DRAIN INSTALLATION, CUT DRAIN LINE TO THE
RIGHT HEIGHT, INSTALL THE COUPLING, 2" PVC PIPE AND DRAIN, CHECK DRAIN
FOR LEVEL, TAPE UP THE STRAINER TO PREVENT DIRT FROM ENTERING THE 
DRAIN LINE. MIX UP THE MUD TO BACK FILL ( WET MUD, PORTLAND AND SAND ONLY)
MIXING THE DRAIN MUD:
PUT ENOUGH PORTLAND AND SAND AS NEEDED IN A BUCKET
HAVE 2 BUCKETS OF WATER READY , MIX UP THE MIXTURE WITH WATER
USING THE SQUARE PALITA. IF LARGE AMOUNT OF CEMENT IS NEEDED 
HOOK UP THE DRILL WITH THE MIXING PADDLE .
CLEAN UP ALL TOOLS AND BRING IN CEMENT.
P10WOOD RECONSTRUCTION
TOOLS NEEDED:
PRIMARY, SECONDARY TOOL BOXES , PASLODE NAILER WITH FASTENERS
AIR COMPRESSOR, AIR HOSE, NAIL GUN, 8S & 12S NAILS, NAIL GUN OIL,
POWER DRIVER WITH NAILS & BLANKS, MASK, GOGGLES , EAR PLUGS, GLOVES,
POUCH W/ SCREWS, RYOBI, 2 ,3 ,4 ,6 ' LEVELS, CARPENTER'S PENCIL,
MEASURING TAPE, HORSES, ZAW-ZALL WITH METAL BLADE, THREE WAY CORD
SPEED SQUARE , CHALKING GUN , 
MATERIALS NEEDED
FASTENERS , SCREWS , 2X4S WHITE WOOD STUDS , 2X4 WALMANIZED 
PROCEDURE
HOOK UP THE COMPRESSOR AND NAIL GUN WITH OIL
HOOK UP THE SAFETY EQUIPMENT
BRING IN ALL THE OTHER TOOLS AS SPECIFIED
SET UP FOR CUTTING WOOD OUTSIDE AND INSIDE
INSPECT THE EXISTING STRUCTURE TO FORMULATE A SOLUTION TO RESTORE
THE STRUCTURE INTEGRITY OF THE SHOWER STALL
REPLACE ALL DAMAGED AND ROTTED FLOORPLATES
REINFORCE ALL WALL STUDS , RECONSTRUCT SHOWER CURB AND JAM
P11FAUCET INSTALLATION
REPLACING THE SHOWER OR THE TUB SHOWER FAUCET
TOOLS NEEDED 
PRIMARY AND SECONDARY AND PLUMBING TOOL BOXES / RIUBI  
POUCH W SCREWS /FOUR WAY SCREW DRIVER / GREY TUBE CUTTER
CIRCULAR SAW, EXTENSION CORD, HORSES, SPEED SQUARE
ASSORTED PIPE WRENCHES AND CHANNEL LOCK PLIERS
ZAW-ZALL, TIN SNIPS, 
MATERIALS NEEDED
2X4S WHITE WOOD STUDS ( INSIDE)
COPPER LINE & FITTING , PLUMBING STRAP,
SHOWER FAUCET
TEFLON TAPE
DRYWALL SCREWS
PROCEDURE
TURN OFF THE WATER SUPPLY TO THE HOUSE AND DRAIN WITH SPICKET
SET UP WORK AREA WITH ALL THE TOOLS AND MATERIALS NEEDED.
FROM THE PLUMBING BOX RETRIEVE THE FOLLOWING:
TORCH, SOLDER, FLUX WITH THE BRUSH, 4 IN 1 SANDING TOOL, 4 COPPER 
MALE ADAPTERS, COUPLINGS, 10' OF COPPER TUBING
1 BUCKET OF WATER WITH A SPONGE, TEFLON TAPE, FIRE EXTINGUISHER
SAND ALL THE FITTINGS TO BE USED , PREP THE FAUCET
REMOVE OLD FAUCET, MODIFY SUPPLY LINES AS NEEDED
INSTALL 2X4 SUPPORT FOR FAUCET AND SHOWER HEAD
INSTALL NEW FAUCET AND CHECK FOR THE CORRECT DEPTH
PLUMB IN SHOWER HEAD SUPPLY LINE WITH EARED ELBOW
INSTALL NIPPLES WITH CAPS AS NEEDED
TURN ON WATER AND CHECK FOR LEAKS
P12SHOWERPAN 40 MIL INSTALLATION
TOOLS NEEDED 
PRIMARY, SECONDARY, & PLUMBING TOOL BOXES , BLADE
PALITA, TIN SNIPS, BLADE, MAGIC MARKER, STAPLER AND STAPLES, 
7/16" DEEP SOCKET WITH QUARTER INCH RATCHET/ SCISSORS
MATERIALS NEEDED
SHOWER PAN, PVC PRIMER AND GLUE, MASKING TAPE
PROCEDURE
CLEAN UP SHOWER STALL FLOOR, LAY PAN OUT, STAPLE AS NEEDED,
MAKE FOLD ON CURB, CUT AS MARKED, 
P13LIGHT/HEATER/VENT INSTALLATION
TOOLS NEEDED 
PRIMARY AND SECONDARY & ELECTRICAL TOOL BOXES /FOUR WAY SCREWDRIVER
THREE WAY EXTENSION CORD  / ROTO ZIP AND TIPS /  RIUBI
FOUR WAY SCREWDRIVER / ZAW-ZALL WITH  SHEETROCK BLADE
YELLOW PIG TAIL ELECTRICAL TESTER / SCREW GUN / LOADED POUCH
SAFETY EQUIPMENT / FISH LINE
MATERIALS NEEDED
LIGHT/HEATER/VENT UNIT  / WIRE NUTS / ELECTRICAL TAPE / 
LIGHT SWITCH WITH BOX
ROMEX
PROCEDURE
BRING ALL ITEMS AND TOOLS NEED AS NOTED ABOVE.
STRAP ON POUCH, CUT CEILING AND INSTALL UNIT. 
MAKE ALL CONNECTIONS TO THE UNIT, 
RUN THE ROMEX TO GET ELECTRICAL POWER
TEST UNIT AND INSTALL ALL TRIMMINGS
P14SHEETROCK INSTALLATION
PROCEDURE
TOOLS NEEDED
HORSES,  CARPENTER'S PENCIL, BLADE, MEASURING TAPE
4' LEVEL & STRAIGHT EDGES, CHALK LINE ,CHEESE GRADER 
SHEETROCK SQUARE , LOADED POUCH , RIUBI COMBO SET, DRYWALL SCREWS
FASTENER BUCKET WITH ASSORTED SCREWS
MATERIALS NEEDED
SHEETROCK
PROCEDURE
SET UP HORSES , PUT TWO 2X4S ACROSS THE HORSES, LAY SHEETROCK ON HORSES
MEASURE SHEETROCK, CUT AND GRADE , 
BRING IN ALL CUTS. HOLD IN POSITION AND INSTALL
P15HARDI-BOARD/DUROCK
PROCEDURE
TOOLS NEEDED
HORSES, GRINDER, CARPENTER'S PENCIL, CARBIDE SCORING TOOL, BLADE
EXTENSION CORD, VACCUME CLEANER WITH WATER , MASK, GOGGLES , EAR PLUGS
4' LEVEL & STRAIGHT EDGES, CHALK LINE, WATER BUCKET AND SPONGE
MATERIALS NEEDED
HARDI BOARDS 
PROCEDURE
CUT THE HARDI WITH THE GRINDER AND VACCUME CLEANER FOR DUST
BRUSH OFF HARDI WHEN CUT AND CLEAN OFF WITH WET SPONGE
P16MUD SETTING THE TOP & INSIDE OF CURB
MUDSETTING IS A MIXTURE OF SAND , PORTLAND ,& MASONARY
THIS IS A WET MIXTURE TO ALLOW IT TO BE PLASTERED TO THE LATH
TOOLS NEEDED:
BATCH BOX, HOE, SHOVEL, 2 BUCKETS OF WATER,2 EMPTY BUCKETS, SPONGE
TARP, TIN SNIPS, MUD TROWEL, MUD HOG,, STAND AND MUD BOARD
2' , 3', 4' AND TORPEDO LEVELS, SHOWER CURB  C CLAMPS , HAMMER STAPLER 
STAPLES,  PALITAS, POINTER
MATERIALS NEEDED 
SAND , PORTLAND, MASONARY, METAL LATH,, BAKING SODA
LATEX GLOVES, 1X3 OR 1X4 FOR GAUGES
PROCEDURE
CUT METAL LATH TO SPECIFIED SIZE, CUT 1X3s TO SIZE
INSTALL LATH
LAYOUT THE TARP WHERE MUD WILL BE MIXED
MIX UP MUD IN BATCH BOX ON TARP
BRING IN MUD AND ALL THE TOOLS AND MATERIALS LISTED ABOVE
P17SHOWERBENCH CONSTRUCTION
MUDSETTING IS A MIXTURE OF SAND , PORTLAND ,& MASONARY
TOOLS NEEDED:
BATCH BOX, HOE, SHOVEL, 2 BUCKETS OF WATER,2 EMPTY BUCKETS, SPONGE
TARP, MUD TROWEL, MUD HOG,, STAND AND MUD BOARD
2' , 3', 4' AND TORPEDO LEVELS,
TROWELS,  PALITAS, POINTER, MALLET, 
MATERIALS NEEDED 
SAND , PORTLAND, MASONARY ,CINDER BLOCKS, BAKING SODA
LATEX GLOVES, 1X3 OR 1X4 FOR GAUGES / SCRAPS/DEBRIS TO BACK FILL
THE HOLLOW AREAS IN THE CINDER BLOCKS
PROCEDURE
LAYOUT THE TARP WHERE MUD WILL BE MIXED
MIX UP MUD IN BATCH BOX ON TARP
BRING IN MUD AND ALL THE TOOLS AND MATERIALS LISTED ABOVE
DRY SET THE CINDER BLOCKS TO CONFIRM THE LAY-OUT
P18SET-UP FOR SHOWER TILE INSTALLATION
WHILE DOING THIS PROCEDURE IT WILL BE NECESSARY TO DO A MODIFIED MUD
PACKING.
SEE MUD PACKING SHOWER FLOOR
TOOLS NEEDED 
PRIMARY AND SECONDARY TOOL BOXES / TILE CUTTER WITH WD-40, NIPPERS,
STAND WITH MUD BOARD,2,3,4,6' LEVELS, CARPENTER'S PENCIL, SHARPIE,
SPEED SQUARE, THIN SET AND MASTIC TROWELS, PALITA AND POINTERS,
RYOBI LIGHT AND SCREW GUN, HAMMER, RUBBING STONE, WATER BUCKET&
SPONGE, TRASH BUCKET, CHEATERS, HAMMER DRILL & HOLE SAW WITH
EXTENSION CORD, SET-UP WET SAW, YELLOW SQUARE
MATERIALS NEEDED
WALL TILE, BASE, CAPS, MASTIC AND/OR THIN SET
PROCEDURE
CLEAN AND SET UP WORK AREA, BRING IN ALL THE TILE, MUD PACKING, 
MUD PACK THE EDGES, LEVEL OUT , SPREAD MASTIC THREE ROWS WITH BASE
INCLUDED, LEVEL OUT WALL TILE, CONTINUE SETTING TILE TO THE TOP
FOR DESIGNED SHOWERS, CUT ALL THE NEEDED TILE ON THE WET SAW.
ALSO CUT ALL MITER CUTS FOR CAPS NEEDED ON THIS JOB
INSTALL CADDY CORNERS AND CUT OUT FOR ALL ACCESSORIES
P19WET SAW 
HOOK UP EXTENSION CORD, SET UP HORSES
SET UP WET SAW ON MUD BOARD ON TOP OF HORSES
HOOK UP WATER PUMP AND FILL WETSAW TUB WITH WATER
SPRAY WET SAW PLATE WHEELS WITH WD40 BEFORE USING
HAVE TEMP PLATES FOR CUT AND EMPTY BUCKET FOR TRASH
P20GROUTING & FINISH PLUMBING SHOWER
GROUT OUT ALL TILE WORK, INSTALL FAUCET TRIM PIECES, & ACCESSORIES
TOOLS NEEDED 
MIXER, EXTENSION CORD, PADDLE, TARP, BUCKETS, SPONGES, GROUT FLOATS
PALITA, POINTERS, GROUT BUCKET, SIFTER, HACK SAW, SHARPIE, CHANNEL LOCKS
FOUR WAY SCREW DRIVER, RYOBI, 
MATERIALS NEEDED
LATEX GLOVES, GROUT, 8 BUCKETS FILLED WITH WATER, MASKING TAPE
SOAP DISH, TOWEL BAR, TEFLON TAPE, FAUCET TRIM PIECES
PROCEDURE
CLEAN AND SET UP WORK AREA, MASK ALL ALONG THE TILE EDGES
BRING IN TOOLS, FAUCET TRIM PIECES, GROUT, WATER, & SPONGES
SPREAD GROUT, CLEAN OFF ACCESS GROUT, INSTALL ACCESSORIES & CLEAN
POLISH TILE WORK, INSTALL FAUCET TRIM
REMOVE MASKING TAPE, CLEAN UP BATHROOM TILEWORK
P21MUDPACKING SHOWERPAN
TOOLS NEEDED:
THIN SET TROWEL/ MUD TROWEL / POINTER / PALITA /  MASK / LATEX GLOVES/
STRAINER HOUSING / SHARPIE / TILECUTTER WITH WD40 / KNEE PADS/
BEATER BOARDS / GRADERS / DUST PAN & BRUSH / NIPPERS / SPEED SQUARE
2 & 3 FEET LEVELS / LIGHT / WETSAW SETUP / HOE / SHOVEL / SPONGES
2 WHEEL DOLLY
MATERIALS NEEDED
SAND / PORTLAND CEMENT / FLOOR TILE / POWDER THIN SET / 
PROCEDURE MAKING THE MUD
LAYOUT THE TARP WHERE MUD WILL BE MIXED
SETUP MUD BOX / SHOVEL / HOE / 2 BUCKETS OF WATER / 
BRING MATERIALS NEXT TO THE BOX
POUR IN SAND AND PORTLAND 3 PARTS SAND TO 1 PART PORTLAND
MIX WITH HOE AND SHOVEL AS NEEDED
ONCE THE MATERIALS ARE MIXED THOROUGHLY / START SPRINKLING
WATER OVER THE MATERIALS WITH A SPONGE. 
PAY CLOSE ATTENTION NOT TO OVER SATURATE THE MIXTURE MAKING IT WET-MUD
SHIFT MUD BACK AND FORTH IN THE BATCH BOX UNTIL IT IS MOIST
FILL THE BUCKETS WITH THE MUD AND BRING INTO BATHROOM WITH DOLLY
BRING IN MUD AND ALL THE TOOLS AND MATERIALS LISTED ABOVE
AFTER MUD IS MADE CLEAN OFF ALL THE TOOLS USED
PROCEDURE INSTALLING SHOWER DRAIN BEFORE MUD PACKING
P22GROUT SHOWER FLOOR
ITEMS NEEDED FOR GROUTING SHOULD ALREADY BE SET UP FROM
GROUTING SHOWER.
MAKE SURE THAT THE GROUT FOR THE SHOWER FLOOR IS VERY STIFF
P23 SLIDING SHOWER DOOR INSTALLATION
TOOLS NEEDED ;
PUNCH, HAMMER DRILL, 3/16" MASONRY DRILL BIT, POUCH
RYOBI SCREWGUN, HACKSAW, MEASURING TAPE, SHARPIE,
CHALKING GUN, 6-8 PLASTIC PLUGS, HAMMER, PENCIL,
WATER BUCKET & SPONGE, (EXTENSION CORD IF HAMMERDRILL IS USED)
  
MATERIALS NEEDED:
SHOWER DOOR, CHALKING, SCREWS, 
PROCEDURE
OPEN UP DOOR PACKAGE, SORT OUT ALL THE HARDWARE
MAKE SURE ALL THE PIECES ARE THERE,
SETUP THE JOB SITE WITH ALL THE ABOVE TOOLS
MEASURE THE THRESHOLD AND CUT IT TO SIZE,
SET IT ON THE CURB, PLACE STRIKE JAM IN PLACE
PUNCH THE MARKS AND MAKE THE HOLE
INSERT THE PLUGS, LINE UP JAM AND INSTALL
MARK , DRILL, PLUG, AND INSTALL
MEASURE THE  HEADER , CUT ,& PLACE
ASSEMBLE THE GLASS PANES WITH WHEELS
SMALLER OF THE PANE GOES ON THE OUTSIDE
ADJUST TO CLOSE PROPERLY
INSTALL BOTTOM GUIDES 
INSTALL SHOWER DOOR HANDLES 
SMALL ONE IN THE INSIDE PANEL
TOWEL BAR ON THE OUTSIDE PANEL
CHALK THE JAMS AND THRESHOLD
CLEAN UP AREA  DOUBLE CHECK OPERATIONS ETC……….
P24RESTROOM FLOOR TILE INSTALLATION
PROCEDURE
TOOLS NEEDED:
TARP, 3 WATER BUCKETS, EXTENSION CORD, DRILL MIXER, MIXING PADDLE
THIN SET BUCKET, 3 SPONGES, PALITA, POINTER, THIN SET TROWEL
MEASURING TAPE, SHARPIE, SPEED SQUARE, TILE CUTTER , CLOSET FLANGE
WD40, KNEES PADS, CARPENTER SQUARE, SPACERS, STRAIGHT EDGES
CHALK LINE,  PRIMARY TOOL BOX, GRINDER & UNDER CUT SAW 
WET SAW SET UP, 8" SCRAPER, ALL LEVELS
MATERIALS NEEDED
TILE , THIN SET, SPACERS , MASKING TAPE , FINISH NAILS, 
PRE THE FLOOR
REMOVE THE SHOE MOLDING. CUT THE SEAM ON WALL AND FLOOR WITH THE BLADE 
REMOVE FIXTURES , REMOVE THE FLOOR COVERING WITH SCRAPER , 
DRY RUN LAYOUT, MIX THIN SET , SET TILE 
OUTSIDE PREP
ON THE TARP, CONNECT THE EXTENSION CORD , MIXER, & PADDLE
MIX THE THIN SET, CLEAN THE PADDLE, BRING IN THE THIN SET,
TILE, 1 WATER BUCKET WITH A SPONGE, 
SET UP THE WET SAW  STRATIGICLY
BRING IN ALL THE OTHER TOOLS LISTED ABOVE AS NEEDED
P25VANITY INSTALLATION
INSTALLATION OF THE BOTTOM CABINETS IN THE BATH ROOM
AND MEDICINE CABINET
TOOLS NEEDED 
PRIMARY AND SECONDARY TOOL BOXES / RIUBI / STUD FINDER / POUCH W SCREWS
2 , 3 , & 4 FOOT LEVELS / FOUR WAY SCREW DRIVER / DRILL BIT SET
MATERIALS NEEDED
CABINETS / WOOD CHIMES / DRYWALL SCREWS / 
PROCEDURE
SET UP WORK AREA
ASSEMBLE CABINETS AS NEEDED
PLACE CABINETS WHERE THEY ARE GOING TO BE INSTALLED
FASTEN CABINETS TO THE WALL    FOR MORE THAN
ONE CABINET, FASTEN THE CABINETS TO EACH OTHER FIRST DRILLING
A PILOT HOLE  TO AVOID SLITTING THE CABINETS THEN THE SCREWS 
SHIM AND LEVEL BEFORE FINAL INSTALLATION
P26R & R MEDICINE CABINET INSTALLATION
TOOLS NEEDED 
SCREW GUN / STUD FINDER / POUCH AND SCREWS / PRY BAR / BLADE / PUTTY KNIFE / 
SHEETROCK SAW / ROTO ZIP AND BITS / 
MATERIALS NEEDED
MEDICINE CABINET
PROCEDURE
REMOVE OLD CABINET . MARK OUT WHERE THE NEW CABINET WILL GO . 
MAKE THE NESSECARY MODIFICATION TO THE WALL TO ACCOMMODATE THE NEW CABINET
ASSEMBLE THE CABINET AS PER INSTRUCTIONS.
LEVEL THE CABINET AND INSTALL WITH DRY WALL SCREWS.
P27LAVATORY, FAUCET,& DRAIN INSTALLATION
TOOLS NEEDED 
PRIMARY AND SECONDARY & PLUMBING TOOL BOXES /FOUR WAY SCREWDRIVER
THREE WAY EXTENSION CORD  / BROOM / DUST PAN / RIUBI / PRY BARS
FOUR WAY SCREWDRIVER , ASSORTED CHANNELS LOCKS & PIPE WRENCHES,
ASSORTED CRESCENT WRENCHES, BASIN WRENCH,  ZAW-ZALL/ METAL BLADE
CHALKING GUN , BUCKET WITH WATER AND SPONGE
SPONGE FOR BACK WHILE LAYING IN THE CABINET
MATERIALS NEEDED
LAVATORY, TWO ANGLE STOPS, ASSORTED NIPPLES, 2 HALF INCH ESCUSIONS,
1 1/2" ESCUSIONS FOR DRAIN LINE, 1 1/2" PETE TRAP, 1 1/4" TAIL PIPE EXTENSION
PLUMBER'S PUTTY, TEFLON TAPE, WD-40, 2 WATER SUPPLY LINES, 
PROCEDURE
TURN OFF WATER AND DRAIN SYSTEM BEFORE STARTING
SET UP WORK AREA, INSTALL THE FAUCET ON THE LAVATORY, INSTALL THE WATER
LINES ON THE FAUCET, INSTALL THE TAILPIPE AND STOPPER ASSEMBLY , INSTALL
THE ESCUSIONS AND ANGLE STOPS ON THE WALL, PREP DRAIN LINE COMING
OUT OF THE WALL. DROP IN SINK, HOOK UP WATER LINES, INSTALL DRAIN LINE, 
CHALK SEAMS ON SINK, REMOVE FAUCET STRAINER ,TURN WATER ON,
BLEED DEBRIS FROM WATER LINE, REINSTALL STRAINER, CHECK FOR LEAKS
P28COMMODE INSTALLATION
INSURE THAT THE BOTTOM OF THE COMMODE IS CLEAN
HANDLE THE COMMODE WITH CARE
TOOLS NEEDED 
7/16" DEEP SOCKET / 1/4" RATCHET / MEDIUM CHANNEL LOCKS (BLUE)  
BOLT CUTTERS / HACKSAW / SMALL BUCKET
MATERIALS NEEDED
WAX RING /  CLOSET BOLTS / ANGLE STOP / SUPPLY LINE/
CHIMES OR SPARE CHANGE .
PROCEDURE
TURN OFF WATER AND OPEN UP OUTSIDE  WATER SPICKET TO DRAIN WATER LINE
INSTALL ANGLE STOP / ESCUSIONS AND SUPPLY LINE ( WHEN NEEDED) 
PUT WAX RING ON THE BOTTOM OF THE COMMODE.
SET THE COMMODE INTO PLACE / BACK FILL WITH GROUT TO STABILIZE BASE
TIGHTEN UP THE CLOSET BOLTS AND CUT. MAKE SURE TO USE THE WASHERS
SHIM IN COMMODE AS NEEDED.
CONNECT WATER SUPPLY LINE AND BLEED DEBRIS
TURN ON WATER AND TEST FOR LEAKS
P29GROUTING RR FLOOR
PROCEDURE
TOOLS NEEDED:
TARP, 5-8 WATER BUCKETS, EXTENSION CORD, DRILL MIXER, MIXING PADDLE
GROUT BUCKET, 3 SPONGES, PALITA, POINTER, GROUT FLOATS
MEASURING TAPE, SHARPIE, MASKING TAPE, NEEDLE NOSE PLIERS
WD40, KNEES PADS, PRIMARY TOOL BOX
MATERIALS NEEDED
GROUT
PROCEDURE
LAY OUT TARP AND WEIGHT IT DOWN , PUT THE GROUT, SIFTER, AND WATER
ON THE TARP, CONNECT THE EXTENSION CORD , MIXER, & PADDLE
MIX THE GROUT, CLEAN THE PADDLE, BRING IN THE GROUT AND WATER BUCKETS,
3 SPONGES 
BRING IN ALL THE OTHER TOOLS LISTED ABOVE AS NEEDED
REMOVE SPACERS / CLEAN FLOOR / GROUT OUT FLOOR
AFTER IT DRIES FOR A WHILE / CLEAN OFF ACCESS GROUT WITH MOIST SPONGES
POLISH FLOOR
P30WRAP UP PHASE
POLISH NEW TILE WORK 
CLEAN UP WORK AREAS
CLEAN UP ALL TOOLS AND EQUIPMENT USED ON THIS JOB
STRAIGHTEN OUT VAN
LOAD UP ALL TOOLS AND TRASH
P31DECONSTRUCTING TT
PROCEDURE LIST
IN THIS PROCEDURE IT IS NECESSARY TO PROTECT THE TUB
IF THE  TUB IS NO TO BE REPLACED.
TOOLS NEEDED:
MATERIALS
MASKING TAPE / PAPER / 
PROCEDURE
MASK THE TUB AND LAY PAPER FOR PROTECTION
INSTALL EXHAUST WINDOW FAN W/ EXTENSION CORD
REMOVE THE FAUCET FIXTURES AND SAVE IN CABINET
REMOVE ALL THE VERTICAL TRIM TILE
DRAW A PLUM LINE WHERE WALLS WILL BE REMOVED
CONNECT ZALL-ZAW AND VACCUME CLEANER
MAKE 2 VERTICAL CUTS AS DRAWN AND ABOVE HORIZONTAL TILE
FIND STUDS AND REMOVE THE SMALL WALLS
REMOVE NAILS AND CONTINUE TO REMOVE BIG WALL
CLEAN UP WALL STUDS OF NAILS AND DEBRIS
P32TUB REMOVAL
PROCEDURE
TOOLS NEEDED:
RIUBI SCREWGUN / POUCH / STANDARD SCREWDRIVER / DUMBBELL DRAIN REMOVER
PRYBARS / HAMMER / SCRAPS OF 2X4S / POSSIBLE POWER SCRAPER
 
MATERIALS NEEDED:
PROCEDURE:
REMOVE ALL TUB HANGERS FASTENERS IF THEY ARE THERE
REMOVE THE TRIP LEVER AND FACING FROM TUB
REMOVE THE TUB DRAIN USING THE DUMBBELL OR TWO SCREWDRIVERS
CLEAN UP THE STUDS SO THE TUB WILL COME OUT EASILY
PRY BATHTUB OFF THE FLOOR
TAKE THE BATH TUB OUT TO THE YARD
CLEAN UP THE AREA WHERE THE BATH TUB WAS
P33DECONSTRUCTING TT & WAIN COATING
PROCEDURE LIST
IN THIS PROCEDURE IT IS NECESSARY TO PROTECT THE TUB
IF THE  TUB IS NO TO BE REPLACED.
TOOLS NEEDED:
PRIMARY AND SECONDARY TOOL BOXES / ZAW-ZALL / 
THREE WAY EXTENSION CORD / EMPTY BUCKETS / BROOM / DUST PAN 
MASK GOGGLES/ GLOVES / EAR PLUGS / PALITA / RIUBI / PRY BARS,
FOUR WAY SCREWDRIVER / STUD FINDER / LOADED POUCH/ CHANNEL LOCKS
CONNECT THE VACCUME CLEANER W/WATER  / WINDOW FAN
POSSIBLE ALLEN WRENCH SET FOR TUB FILLER
MATERIALS
MASKING TAPE / PAPER / 
PROCEDURE
CUT AND SEPARATE THE EDGE OF ALL THE TRIM TILE TO BE REMOVED
REMOVE THE FAUCET FIXTURES AND SAVE IN CABINET
REMOVE ALL THE VERTICAL TRIM TILE
DRAW A PLUM LINE WHERE WALLS WILL BE REMOVED
CONNECT ZALL-ZAW AND VACCUME CLEANER
MAKE 2 VERTICAL CUTS AS DRAWN AND ABOVE HORIZONTAL TILE
FIND STUDS AND REMOVE THE SMALL WALLS
REMOVE NAILS AND CONTINUE TO REMOVE BIG WALL
CLEAN UP WALL STUDS OF NAILS AND DEBRIS
CONTINUE WITH ALL THE WALL WAINS COATING
P34SET-UP FOR TILE INSTALLATION
PROCEDURE
TOOLS NEEDED 
PRIMARY AND SECONDARY TOOL BOXES / TILE CUTTER WITH WD-40, NIPPERS,
STAND WITH MUD BOARD / ALL LEVELS, CARPENTER'S PENCIL, SHARPIE,
SPEED SQUARE, THIN SET AND MASTIC TROWELS, PALITA AND POINTERS,
RYOBI LIGHT AND SCREW GUN, HAMMER, RUBBING STONE, WATER BUCKET&
SPONGE, TRASH BUCKET,
MATERIALS NEEDED
WALL TILE, CAPS, MASTIC AND/OR THIN SET
PROCEDURE
CLEAN AND SET UP WORK AREA, BRING IN ALL THE TILE, STAND, MUD BOARD
CHEATERS, WD-40, AND ACCESSORIES
MAKE LEVEL LINES , INSTALL TILE, AND CADDIES
CUT OUT FOR SOAP DISH, AND TOWEL BARS
P35GROUTING & FINISH PLUMBING TT
GROUT OUT ALL TILE WORK, INSTALL FAUCET TRIM PIECES, & ACCESSORIES
TOOLS NEEDED 
MIXER, EXTENSION CORD, PADDLE, TARP, BUCKETS, SPONGES, GROUT FLOAT
PALITA, POINTERS, GROUT BUCKET, SIFTER, HACK SAW, SHARPIE, CHANNEL LOCKS
FOUR WAY SCREW DRIVER, RYOBI , CHALKING GUN
MATERIALS NEEDED
LATEX GLOVES, GROUT, 8 BUCKETS FILLED WITH WATER, MASKING TAPE
SOAP DISH, TOWEL BAR, TEFLON TAPE, FAUCET TRIM PIECES
CHALKING
PROCEDURE
CLEAN AND SET UP WORK AREA, MASK ALL ALONG THE TILE EDGES
BRING IN TOOLS, FAUCET TRIM PIECES, GROUT, WATER, & SPONGES
SPREAD GROUT, CLEAN OFF ACCESS GROUT, INSTALL ACCESSORIES & CLEAN
NOTE: IT MAY BE NECESSARY TO SET UP FOR PLUMBING AT THIS TIME
PLUMBING BOX, COPPER PIPE, 2 MALE ADAPTERS, 
PROCESS; SWEAT IN MALE ADAPTER, TEFLON TAPE IT , INSTALL IT
CUT TO SIZE, SWEAT MALE ADAPTER, TEFLON IT INSTALL TUB FILLER
CHALK THE ESCUSIONS
POLISH TILE WORK, INSTALL FAUCET TRIM
REMOVE MASKING TAPE, CLEAN UP BATHROOM
P36TAPE& FLOATING HARDI BACKER JOINTS
TOOLS NEEDED
BLADE / SCISSORS / COMPOUND CONTAINER / PALITA / DRILL MIXER / PADDLE / BUCKET
FLOATING KNIFES (ALL KNIFES INCLUDING CORNER KNIFE) / SPONGES / HAMMER / 
SCREW GUN / BUCKET W/ WATER
MATERIALS NEEDED
THIN SET / FIBERGLASS TAPE / 
PROCESS
SET UP TO MAKE THIN SET
MIX UP THIN SET AND BRING IN ALL THE TOOLS NEEDED AND THE THIN SET
PUT TAPE ON THE JOINTS AND FLOAT THEM OUT WITH THIN SET. 
TOUCH UP THE FLOATED JOINTS
P37FLOOR TILE INSTALLATION
PROCEDURE
TOOLS NEEDED:
TARP, 3 WATER BUCKETS, EXTENSION CORD, DRILL MIXER, MIXING PADDLE
THIN SET BUCKET, 3 SPONGES, PALITA, POINTER, THIN SET TROWEL
MEASURING TAPE, SHARPIE, SPEED SQUARE, GREEN TILE CUTTER
WD40, KNEES PADS, CARPENTER SQUARE, SPACERS, STRAIGHT EDGES
CHALK LINE,  PRIMARY TOOL BOX, GRINDER & UNDER CUT SAW 
WET SAW SET UP, 8" SCRAPER, ALL LEVELS , CLOSET FLANGE
MATERIALS NEEDED
TILE , THIN SET, SPACERS
PREP THE FLOOR
DO THE LAY OUT, BRING IN TILE
PROCEDURE
LAY OUT TARP AND WEIGHT IT DOWN , PUT THE THIN SET AND WATER
ON THE TARP, CONNECT THE EXTENSION CORD , MIXER, & PADDLE
MIX THE THIN SET, CLEAN THE PADDLE, BRING IN THE THIN SET,
TILE, 1 WATER BUCKET WITH A SPONGE, 
SET UP THE WET SAW  STRATIGICLY
BRING IN ALL THE OTHER TOOLS LISTED ABOVE AS NEEDED
DRY RUN, CUT OUT CLOSET FLANGE, INSTALL TILE
P38TUB INSTALLATION
PROCEDURE
TOOLS NEEDED:
RIUBI SCREWGUN, POUCH, CIRCULAR SAW, EXTENSION CORD,
PLUMBING BOX OF TOOLS, MEASURING TAPE, 2', 3', & 4' LEVELS 
STANDARD SCREWDRIVER, 
MATERIALS NEEDED:
TUB, TRIP/WASTE/& OVERFLOW, PLUMBER'S PUDDY,WD40
DUMB BELL DRAIN TOOL, CARDBOARD FOR TUB PROTECTION
1"X 3" OR 1"X4" ABOUT 61" LONG
PROCEDURE:
AFTER THE OLD TUB IS REMOVED, CHECK FLOOR FOR LEVELNESS
MEASURE NEW TUB FROM THE FLOOR TO UNDER THE LIP,
FIND THE HIGH SIDE OF THE FLOOR , MARK THE MEASUREMENT TAKEN FROM
THE TUB, DRAW A LEVEL LINE ACROSS THE BACK WALL WHERE THE TUB
WILL BE INSTALLED, INSTALL A PIECE OF 1X3 AT THE LEVEL LINE
PREINSTALL THE DRAIN LINE ON THE TUB,
INSTALL THE TUB, MAKE NECESSARY ADJUSTMENTS TO THE DRAIN LINE
TIGHTEN UP DRAIN LINE. SPRAY WD40 ON BOTTOM DRAIN WHERE
PLUMBER'S PUTTY WILL BE. TIGHTEN UP BOTTOM DRAIN
INSTALL OVERFLOW COVER WITH BLACK GASKET INCLUDED
SCREW DRYWALL SCREWS RIGHT ABOVE TUB TO SECURE IT FROM 
MOVING UP. RUN A WATER TEST FOR LEAKS.
P39DECONSTRUCTING FIBERGLASS 
TUB/SHOWER COMBINATION
PROCEDURE LIST
TOOLS NEEDED:
PRIMARY AND SECONDARY TOOL BOXES / ZAW-ZALL / 
THREE WAY EXTENSION CORD / EMPTY BUCKETS / BROOM / DUST PAN 
MASK GOGGLES/ GLOVES / EAR PLUGS / PALITA / RIUBI / PRY BARS,
FOUR WAY SCREWDRIVER / STUD FINDER / POUCH/ CHANNEL LOCKS
CONNECT THE VACCUME CLEANER W/WATER
POSSIBLE ALLEN WRENCH SET FOR TUB FILLER
PROCEDURE
REMOVE THE FAUCET FIXTURES AND SAVE IN CABINET
REMOVE TRIP/WASTE AND OVERFLOW UNIT
CONNECT ZALL-ZAW AND VACCUME CLEANER
MAKE 2 VERTICAL CUTS THROUGH THE TUBS BIG WALL
THIS WILL SEPARATE THE TUB INTO 3 PIECES
CUT AROUND FIBERGLASS UNIT SEAMS
REMOVE NAILS AND FREE UNIT FROM WALL
REMOVE PIECES
P40GROUTING FLOOR
PROCEDURE
TOOLS NEEDED:
TARP, 5-8 WATER BUCKETS, EXTENSION CORD, DRILL MIXER, MIXING PADDLE
GROUT BUCKET, 3 SPONGES, PALITA, POINTER, GROUT FLOAT
MEASURING TAPE, SHARPIE, MASKING TAPE, NEEDLE NOSE PLIERS
WD40, KNEES PADS, PRIMARY TOOL BOX
MATERIALS NEEDED
GROUT
PROCEDURE
LAY OUT TARP AND WEIGHT IT DOWN , PUT THE GROUT,  SIFTER, AND WATER
ON THE TARP, CONNECT THE EXTENSION CORD , MIXER, & PADDLE
MIX THE GROUT, CLEAN THE PADDLE, BRING IN THE GROUT AND WATER BUCKETS,
3 SPONGES 
BRING IN ALL THE OTHER TOOLS LISTED ABOVE AS NEEDED
P41LAVA. & FAUCET REMOVAL
TOOLS NEEDED:
LARGE AND SMALL  CHANNEL LOCKS ,  SMALL CRESCENT WRENCH/ 
SMALL GROUT BUCKET FOR WATER ,  SPONGE
BASIN WRENCH , RYOBI LIGHT ,  LOADED POUCH  ,  PUTTY KNIFE  
PROCEDURE
INSURE THAT THE WATER HAS BEEN TURNED OFF IF THE ANGLE STOPS
ARE TO BE REMOVED.
TURN OFF THE ANGLE STOPS , PLACE THE GROUT BUCKET UNDER THE
PETE-TRAP TO PREVENT THE WASTE WATER FROM FLOODING THE BOTTOM 
OT THE VANITY CABINET.
DISCONNECT 1 1/2" PETE-TRAP AND DRAIN LINE ,  DRAIN OUT ALL THE WATER
DISCONNECT SUPPLY LINES FROM THE  FAUCET
SEPARATE SINK FROM COUNTER TOP IF THE COUNTER TOP IS A TWO PIECE UNIT
REMOVE LAVATORY SINK
CLEAN UP ALL WATER AND DEBRIS FROM THE WORK AREA AND 
PREPARE FOR THE FOLLOWING STEPS
P42LAVATORY, FAUCET, DRAIN INSTALLATION
CULTURE COUNTER TOP INSTALLATION
TOOLS NEEDED 
PRIMARY AND SECONDARY & PLUMBING TOOL BOXES /FOUR WAY SCREWDRIVER
THREE WAY EXTENSION CORD  / BROOM / DUST PAN / RIUBI / PRY BARS
FOUR WAY SCREWDRIVER , ASSORTED CHANNELS LOCKS & PIPE WRENCHES,
ASSORTED CRESCENT WRENCHES, BASIN WRENCH,  ZAW-ZALL/ METAL BLADE
CHALKING GUN , BUCKET WITH WATER AND SPONGE
SPONGE FOR BACK WHILE LAYING IN THE CABINET
MATERIALS NEEDED
CULTURE COUNTER TOP WITH THE END CAPS
LAVATORY, TWO ANGLE STOPS, ASSORTED NIPPLES, 2 HALF INCH ESCUSIONS,
1 1/2" ESCUSIONS FOR DRAIN LINE, 1 1/2" PETE TRAP, 1 1/4" TAIL PIPE EXTENSION
PLUMBER'S PUTTY, TEFLON TAPE, WD-40, 2 WATER SUPPLY LINES, 
PROCEDURE
SET UP WORK AREA, INSTALL THE FAUCET ON THE LAVATORY, INSTALL THE WATER
LINES ON THE FAUCET, INSTALL THE TAILPIPE AND STOPPER ASSEMBLY , INSTALL
THE ESCUSIONS AND ANGLE STOPS ON THE WALL, PREP DRAIN LINE COMING
OUT OF THE WALL. DROP IN SINK, HOOK UP WATER LINES, INSTALL DRAIN LINE, 
CHALK SEAMS ON SINK, REMOVE FAUCET STRAINER ,TURN WATER ON,
BLEED DEBRIS FROM WATER LINE, REINSTALL STRAINER, CHECK FOR LEAKS
P44SETTING UP  PHASES
CUTTING WOOD
OUTSIDE : HOOK UP EXTENSION CORD WITH THE THREE WAY PLUG
SET UP HORSES
CIRCULAR SAW WITH SPEED SQUARE, CARPENTER'S PENCIL,& MEASURING TAPE
LAY ALL WOOD TO BE CUT ON THE HORSES
WET SAW 
HOOK UP EXTENSION CORD, SET UP HORSES
SET UP WET SAW ON MUD BOARD ON TOP OF HORSES
HOOK UP WATER PUMP IN FULL BUCKET OF WATER
SPRAY WET SAW WHEELS WITH WD40 BEFORE USING
HAVE TEMP PLATES FOR CUT AND EMPTY BUCKET FOR TRASH
HAVE ONE BUCKET FOR SCRAPS PIECES OF TILE AND
ANOTHER BUCKET FOR THE TILES WHICH HAVE BEEN CUT
MUD PACKING
LAYOUT THE TARP WHERE MUD WILL BE MIXED, LAY BATCH BOX ON TARP
BRING ALL THE FOLLOWING ITEMS TO THE TARP
BATCH BOX, TWO EMPTY BUCKETS, TWO BUCKETS OF WATER, SHOVEL, HOE
SPONGE , WATER BOTTLE SPRAYER, SAND, PORTLAND, BAGS OF PRE-MIXED
POUR THE SAND IN THE BOX , FOLLOWED BY THE PORTLAND, MIX WELL
ADD THE WATER AS NEEDED TO MAKE THE MUD PACK MUD
AFTER MUD IS MADE CLEAN OFF ALL THE TOOLS USED
TILE SETTING SETUP
PRIMARY AND SECONDARY TOOL BOXES / TILE CUTTER WITH WD-40, NIPPERS,
STAND WITH MUD BOARD,2,3,4,6' LEVELS, CARPENTER'S PENCIL, SHARPIE,
SPEED SQUARE, THIN SET AND MASTIC TROWELS, PALITA AND POINTERS,
RYOBI LIGHT AND SCREW GUN, HAMMER, RUBBING STONE, WATER BUCKET&
SPONGE, TRASH BUCKET, CHEATERS, HAMMER DRILL & HOLE SAW WITH
EXTENSION CORD,
FAUCET INSTALLATION
SET UP WORK AREA WITH ALL THE TOOLS AND MATERIALS NEEDED.
PRIMARY AND SECONDARY AND PLUMBING TOOL BOXES / RIUBI  
POUCH W SCREWS /FOUR WAY SCREW DRIVER / GREY TUBE CUTTER
CIRCULAR SAW, EXTENSION CORD, HORSES, SPEED SQUARE
ASSORTED PIPE WRENCHES AND CHANNEL LOCK PLIERS
ZAW-ZALL, TINSNIPS, 
FROM THE PLUMBING RETRIEVE THE FOLLOWING
TORCH, SOLDER, FLUX WITH THE BRUSH, 4 IN 1 SANDING TOOL, 
MALE ADAPTERS, COUPLINGS, 10' OF COPPER TUBING
1 BUCKET OF WATER WITH A SPONGE, TEFLON TAPE, 
2X4S WHITE WOOD STUDS 
COPPER FITTING , PLUMBING STRAP,
SHOWER FAUCET
TEFLON TAPE
DRYWALL SCREWS
CUTTING SHEETROCK
LAY ALL SHEETROCK ON AN EVEN AREA
SHEETROCK SQUARE, CHALK LINE, MEASURING TAPE, CARPENTER'S PENCIL
RASP, STRAIGHT EDGES & 4' LEVEL, BLADE, 
HARDI-BOARD/DUROCK
HORSES, GRINDER, CARPENTER'S PENCIL, CARBIDE SCORING TOOL, BLADE
EXTENSION CORD, VACCUME CLEANER WITH WATER , MASK, GOGGLES , EAR PLUGS
4' LEVEL & STRAIGHT EDGES, CHALK LINE, SUPER HARDIE WET SAW
P45TUB TO SHOWER DRAIN CONVERSION
TOOLS NEEDED 
PRIMARY, SECONDARY, & PLUMBING TOOL BOXES , ZAW-ZALL, HAMMER DRILL 
THREE WAY EXTENSION CORD , EMPTY BUCKETS , BROOM , DUST PAN 
MASK GOGGLES , GLOVES ,  EAR PLUGS  , PALITA , RYOBI , POUCH
INSIDE TUBE CUTTER, TORPEDO LEVEL, MAKITA POWER SCRAPER
MAKITA SUPER DEMOLITION HAMMER , EXHAUST FAN , WET-VAC
MATERIALS NEEDED
 2" PVC DRAIN WITH/WITHOUT  GASKET ?????  
PVC PRIMER AND GLUE, MASKING TAPE, 
2"PVC PIPE , 3  2 " COUPLINGS, 1 1/2" TO 2" REDUCER
NO HUB COUPLING 1 1/2" TO 2"
2" PVC PETE TRAP
PROCEDURE
SET UP WORK AREA , START ESCAVALTING THE FOUNDATION TO FACILITATE ACCESS
TO THE DRAIN SYSTEM  / ONCE THIS HAD BEEN ACHIEVED, REMOVE THE TRIP,
WASTE , AND OVERFLOW DRAIN TO TUB CONNECTIONS / REMOVE  THE EXISTING 
PETE-TRAP / CONVERT THE TUB DRAIN SYSTEM TO ACCOMMODATE THE  NEW
SHOWER DRAIN / INSTALL A 2" PETE-TRAP / RUN THE 2" PVC LINE WILD / MEASURE
THE CORRECT HEIGHT AND CUT . INSTALL 2" SHOWER DRAIN / ASSURE THE TOP
OF THE DRAIN IS LEVEL / ATTACHE THE COVERING TO THE SHOWER DRAIN STRAINER
TO PREVENT DEBRIS FROM ENTERING THE DRAIN LINE SYSTEM / 
ONCE THIS PORTION OF THE REPAIR IS COMPLETED SET UP FOR MORTAR WORK
AS DESCRIBED IN PROCEDURE NUMBER 16 WITH THE FOLLOWING EXCEPTION
THE MATERIAL TO BE MIXED WILL BE CONCRETE / BRING IN THE CONCRETE AND POUR
CLEAN UP ALL TOOLS AND PREPARE FOR THE FOLLOWING PROCEDURE
P46SHOWER DOOR PIVOT TYPE INSTALLATION
TOOLS NEEDED ;
PUNCH, HAMMER DRILL, 3/16" MASONRY DRILL BIT, POUCH
RYOBI SCREWGUN, HACKSAW, MEASURING TAPE, SHARPIE,
CHALKING GUN, 6-8 PLASTIC PLUGS, HAMMER, PENCIL,
WATER BUCKET & SPONGE, (EXTENSION CORD IF HAMMERDRILL IS USED)
SHARPIE MARKER , FOUR WAY SCREWDRIVER , 
MATERIALS NEEDED:
SHOWER DOOR, CHALKING, SCREWS, PLUGS , 
PROCEDURE
OPEN UP DOOR PACKAGE, SORT OUT ALL THE HARDWARE
MAKE SURE ALL THE PIECES ARE THERE,
SETUP THE JOB SITE WITH ALL THE ABOVE TOOLS
MEASURE THE THRESHOLD AND CUT IT TO SIZE,
SET IT ON THE CURB, PLACE PIVOT JAM IN PLACE
PUNCH THE MARKS AND DRILL THE CORRESPONDING HOLES
INSERT THE PLUGS, LINE UP THE PIVOT JAM AND INSTALL
ASSEMBLE AND INSTALL THE DOOR PANEL ON THE STRIKE JAM
MAKE ADJUSTMENTS TO THE PANEL SO IT WILL BE ABLE TO HOLD 
THE STRIKE JAM IN PLACE TO MAKE IT'S POSITION
MARK THE LOCATION WHERE THE WALL WILL BE DRILLED
DRILL THE HOLES AND INSTALL THE PLUGS
INSTALL THE STRIKE JAM 
MAKE NECESSARY ADJUSTMENT FOR PROPER DOOR OPERATION
INSTALL SHOWER DOOR HANDLE
CHALK THE JAMS AND THRESHOLD
CLEAN UP AREA  DOUBLE CHECK OPERATIONS ETC……….
P48ZEE BAR INSTALLATION
PROCEDURE
TOOLS NEEDED:
POWER DRIVER, NAILS & BLANKS , POUCH, TIN SNIPS, MEASURING TAPE
PADDY KNIFE, 2X4 ABOUT 12" LONG, WEIGHTS LIKE SLEDGE HAMMER
AND TOOL BOXES TO HOLD DOWN CARPET WHILE IT IS BEING
PREPARED., PALITA, PRIMARY TOOL BOX, 
MATERIALS NEEDED:
ZEE BARS, TACK STRIP, 
PROCEDURE:
CUT THE CARPET WILD,  WHERE THE ZEE BAR IS GOING TO BE INSTALLED
CUT THE ZEE BAR TO FIT ALONG WITH TACK STRIP. INSTALL THE ZEE BAR
UNDER WHERE THE DOOR WILL CLOSE. CUT THE PADDING 1/2" 
SHY OF WHERE THE  ZEE BAR WILL BE. TUCK IN THE CARPET
WITH THE PALITA AND BANG IT DOWN WITH THE HAMMER
P49SHOWERDRAIN INSTALLATION ON PAN
TOOLS NEEDED : 
BLADE / 1/4" SMALL RATCHET WITH 7/16" SOCKET / SMALL & MED. CHANNEL LOCKS
SMALL CRESCENT WRENCH / LASER AND SMALL LEVELS / SPONGE / BUCKET OF WATER
MATERIALS NEEDED:
TOP SHOWER DRAIN FLANGE / STRAINER AND HOUSING / MASKING TAPE / 
PVC PRIMER AND GLUE / 
PROCEDURE ;
CLEAN OF SHOWER PAN WHERE THE DRAIN IS / CUT OUT THE HOLES FOR THE
SHOWER DRAIN BOLTS / CUT OUT THE PAN IN CENTER OF THE DRAIN LINE
APPLY PRIMER BETWEEN DRAIN AND PAN / THEN APPLY GLUE TO SAME
INSTALL TOP FLANGE AND TIGHTEN UP BOLTS
COVER THE STRAINER WITH MASKING TAPE TO PREVENT MUD FROM ENTERING DRAIN
INSTALL STRAINER / ADJUST DRAIN TO THE RIGHT HEIGHT 
1/4" LOWER THAN THE BASE TILE / THIS WILL ALLOW DRAIN OF WATER WHEN 
TILE IS INSTALLED
P50MOLDING D&R OR REPLACEMENT
TOOLS NEEDED :
COMPRESSOR , FINISH NAIL GUN , NAIL GUN OIL , DIKES , HAMMER  
NAIL PUNCH , POWER MITER SAW , SQUARE , MEASURING TAPE , PENCIL , 
4" DIAMOND BLADE GRINDER , COPING SAW , PRY BAR , CHALKING GUN
LOADED POUCH , 5 IN 1 PAINTER'S TOOL ,  EMPTY BUCKET AND SPONGE
ADJUSTABLE SQUARE , MASKING TAPE 
MATERIALS NEEDED :
SHOE AND BASE MOLDING AS REQUIRED
FINISH NAIL 6S AND 8S
CHALKING AND WOOD FILLER
PROCEDURE ; 
SET UP THE HORSE WITH THE MUD BOARD. SET THE MITER SAW ON SAME
RUN THE ELECTRICAL POWER TO THE TOOLS TO BE USED OUTSIDE
BRING ALL THE MATERIAL NEEDED TO THE WORK SITE
GRIND OFF ALL THE NAILS FROM THE MOLDING TO BE REUSED IF ANY
MEASURE AND CUT THE MOLDING AS IT WILL BE INSTALLED
SET UP THE COMPRESSOR INSIDE , CONNECT THE AIR HOSE AND NAIL GUN
CUT AND INSTALL BASE MOLDING FIRST AND CONTINUE WITH THE SHOE MOLDING
COPE ALL END PIECES OF THE MOLDING TO FIT CORRECTLY
COUNTER PUNCH ALL FINISH NAILS AND FILL IN WITH WOOD FILLER
USING THE MASKING TAPE , MASK THE FLOOR AND THE WALL TO PREVENT 
CHALKING SMEARS 
CHALK ALL SEAMS OF THE MOLDINGS
CLEAN UP ALL EXCESS CHALK WITH A WET  SPONGE
CLEAN UP AREA , PUT AWAY ALL TOOLS AND EQUIPMENT USED AND 
PREPARE FOR THE FOLLOWING PROCEDURE
P51GRAB BAR INSTALLATION
TOOLS NEEDED 
HAMMERDRILL / EXTENSION CORD / RYOBI SCREW GUN WITH TIP AND BATTERY
DRILL BITS / MASKING TAPE / SHARPIE / MEASURING TAPE / DRYWALL SCREWS / 
HAMMER / POUCH LOADED / SPONGE AND BUCKET / PRIMARY TOOL BOX /
STUD FINDER/
MATERIALS NEEDED
GRAB BARS / PLUGS / ANCHORS / WALL PLUGS SCREW IN TYPE / 
PROCEDURE
CONFER WITH THE CUSTOMER TO AGREE WHERE IS THE BEST LOCATION 
FOR THE GRAB BARS TO BE INSTALLED. ONCE IT'S AGREED , CONTINUE WITH THE 
FOLLOWING: TAPE THE END CAPS OF THE GRAB BAR TO THE CENTER OF SAME
SO IT WILL NO INTERFERE WITH THE INSTALLATION. MARK THE TOP RIGHT SIDE
TO MAINTAIN THE CORRECT ORIENTATION . MARK THE WALLS WHERE THE ANCHORS WILL
BE INSTALL AND DRILL THE APPROPRIATE HOLES . INSTALL THE WALL ANCHORS AND
INSTALL THE GRAB BAR. TEST FOR STRENGTH AND INSTALL SCREW COVERS
REPEAT THE PROCESS ON ALL THE GRAB BAR TO BE INSTALLED
P52ANGLE STOPS REPLACEMENTS
TOOLS NEEDED  :
PRIMARY AND PLUMBING TOOL BOXES
SMALL , MEDIUM, AND LARGE PIPE WRENCHES , SMALL , MEDIUM CHANNEL LOCKS
INSIDE PIPE HOLDER , MEDIUM CRESCENT WRENCH , SMALL BUCKET , SPONGE
TORCH , BUTANE GAS , FLUX , SOLDER , EMORY CLOTH AND SCRUBBERS , 
TORCH LIGHTER , SMALL AND MEDIUM TUBE CUTTERS , 
MATERIALS NEEDED  :
HALF INCH ANGLE STOPS ( GALVANIZED AND COPPER)
HALF INCH ECSUSION ( GALVANIZED AND COPPER)
ASSORTED HALF INCH GALVANIZED PIPE NIPPLES
HALF INCH COPPER PIPE , MALE AND FEMALE COPPER ADAPTERS
TEFLON TAPE , THREADED JOINT COMPOUND , 
WATER SUPPLY LINE ( 3/8" COMPRESSION INLET TO 5/8" COMMODE OUTLET ) 
PROCEDURE  :
INSURE WATER SUPPLY TO THE RESIDENCES HAD BEEN TURNED OFF
OPEN UP THE WATER HOSE SPICKET OUTSIDE TO DRAIN THE WATER SYSTEM
REMOVE THE COMMODE WATER SUPPLY LINE
OPEN UP THE ANGLE STOP AND DRAIN THE EXCESS WATER INTO THE SMALL BUCKET
ADJUST THE PIPE WRENCH TO HOLD THE GALVANIZED NIPPLE WHILE AT THE SAME
TIME ADJUST THE CRESCENT WRENCH ON THE ANGLE STOP. HOLD THE PIPE WRENCH 
IN PLACE WHILE TURNING THE ANGLE STOP COUNTER-CLOCKWISE
INSURE THAT THE PIPE DOES NOT TURN BREAKING THE SEAL INSIDE THE WALL
REMOVE AND REPLACE THE 1/2" ECSUSION
APPLY TEFLON AND THREADED JOINT COMPOUND ON THE THREADS OF THE NIPPLE
HOLD THE NIPPLE IN PLACE WHILE INSTALLING THE NEW ANGLE STOP WITH THE 
CRESCENT WRENCH ( THE USE OF THE CRESCENT IS TO PREVENT DAMAGE TO THE ANGLE STOP)
INSURE THAT THE FINAL POSITION ON THE ANGLE STOP IS AT 12 O'CLOCK
CLEAN UP THE AREA , PUT UP THE TOOLS , AND SET UP FOR THE NEXT PROCEDURE
P53CLOSET FLANGE REPLACEMENT
TOOLS NEEDED 
PRIMARY, SECONDARY, & PLUMBING TOOL BOXES , HAMMER DRILL 
THREE WAY EXTENSION CORD , EMPTY BUCKETS , 
MASK GOGGLES , GLOVES ,  EAR PLUGS  , PALITA , RYOBI , POUCH
INSIDE TUBE CUTTER, TORPEDO LEVEL, MAKITA POWER SCRAPER
MATERIALS NEEDED
FOUR INCH ADJUSTABLE CLOSET FLANGE AND STANDARD REPLACEMENT FLANGE
FOUR INCH PVC LINE APPROXIMATELY 5 FEET LONG
THREE TO FOUR INCH PVC COUPLING
PROCEDURE
SET UP AREA TO PREPARE FOR THE FOLLOWING WORK TO BE DONE
CLEAN OFF THE CLOSET FLANGE , REMOVE ALL THE WAX AND WAX RING
HEAT UP THE LEAD AND REMOVE IT FROM THE FLANGE
REMOVE THE CLOSET FLANGE ANCHORS AND REMOVE FLANGE
CLEAN UP THE AREA SO THE INSTALLATION OF THE NEW FLANGE WILL
NOT BE INTERFERED WITH . 
MODIFY THE DRAIN LINE TO ACCEPT THE NEW CLOSET FLANGE
LINE UP THE FLANGE AND MARK WHERE THE FOUNDATION WILL HAVE TO BE DRILLED
DRILL THE HOLES IN THE FOUNDATION FOR THE ANCHORS
INSTALL THE FLANGE AND ANCHOR THEM DOWN WITH THE HARDWARE PROVIDED
WITH THE ANCHORS
MAKE SURE THE CLOSET BOLTS SLOTS ARE 
IN THE 9 AND 3 O'CLOCK POSITION
CHECK TO MAKE SURE THE FLANGE IS LEVELED. THIS IS VERY IMPORTANT BECAUSE
IF IS OFF EVEN SLIGHTLY A LOT OF THE WASTE WILL OVERFLOW AND OR BACKUP
INTO THE COMMODE BOWL AND ONTO THE FLOOR CREATING A FLOOD IN THE HOUSE
TAPE UP THE DRAIN INLET TO PREVENT DIRT FROM ENTERING THE 
DRAIN LINE. MIX UP THE MUD TO BACK FILL ( WET MUD, PORTLAND AND SAND ONLY)
MIXING THE DRAIN MUD: SEE PROCEDURE NUMBER 16 MUDSETTING
PUT ENOUGH PORTLAND AND SAND AS NEEDED IN A BUCKET
HAVE 2 BUCKETS OF WATER READY , MIX UP THE MIXTURE WITH WATER
USING THE SQUARE PALITA. IF LARGE AMOUNT OF CEMENT IS NEEDED 
HOOK UP THE DRILL WITH THE MIXING PADDLE .
CLEAN UP ALL TOOLS AND BRING IN CEMENT.
P54
REMOVE DOOR FROM HENGIS
REMOVE CASEMENT MOLDING
REMOVE DOOR JAM
MARK AND CUT OUT OPENING FOR POCKET DOOR
REMOVE STUDS AND 
P101DOOR ENLARGEMENT
TOOLS NEEDED:
PRIMARY, SECONDARY TOOL BOXES , PASLODE FINISH NAILER WITH FASTENERS
PRY BARS, PALITA, POINTER, HORSE STANDS
MASK, GOGGLES , EAR PLUGS, GLOVES, BLADE, HAMMER, 
POUCH W/ SCREWS, RYOBI, 2 ,3 ,4 ,6 ' LEVELS, CARPENTER'S PENCIL,
MEASURING TAPE, ZAW-ZALL WITH METAL BLADE, 
SPEED SQUARE , CHALKING GUN , 
MITER SAW, 
MATERIALS NEEDED
ASSORTED SCREWS , 2X4S WHITE WOOD STUDS , 2X6 OR 2X8 FOR HEADER 
SHIMS ( WOOD, FIBER BOARD, LARGE AND SMALL
DOOR. CASEMENT MOLDING, DOOR LOCK, SPACKLING COMPOUND
PROCEDURE
USE THE BLADE TO SCORE ALL AROUND THE CASEMENT AND SEPARATE THE CASEMENT FROM
THE WALLS. PRY-OFF THE CASEMENTS WITHOUT DAMAGING IT IF IT IS TO BE USED LATER.
USE THE RYOBI ZAW-ALL WITH A METAL BLADE TO REMOVE THE JAM FROM THE CRIPPLER
MARK THE INTERIOR WALL WHERE THE DOOR WILL BE LOCATED WITH A LEVEL
CUT OFF THE INSIDE OF THE WALL WHERE THE DOOR WILL BE.
MAKE SURE THERE IS NO ELETRICAL WIRES BEHINDE THE SHEETROCK
INSERT THE ZAW-ZALL WITH A LONG METAL BLADE BETWEEN THE HEADER AND SHEETROCK
CUT OFF THE NAILS CAREFULLY, REMOVE THE HEADER AND STUD.
CUTOFF BOTTOMPLATE WHERE THE DOOR WILL BE EXTENDING TOWARD
INSTALL NEW STUD , INSTALL THE HEADER, INSTALL THE CRIPPLER
CHECK FOR PLUMB AND LEVEL. .
PREPARE DOOR FOR INSTALLATION
INSTLL IN PLACE WITH THE LOCKING PINS IN DOOR LOCK AREA
INSTALL THE SHIMS TO MAKE LEVEL. INSTALLATION OF THE SHIMS WILL BE WHERE
THE HINGES ARE GOING TO BE INSTALLED.
AFTER DOOR IS TACKED UP. REMOVE LOCKING MECHNISM AND SCREW LARGE SCREW 
THROUGH THE CENTER IF EACH HINGE INTO THE CRIPPLER THROUGH THE SHIMS.
CUT AND INSTALL CASEMENTS MOLDING WITH FINISH PASLODE NAIL GUN
OPEM, PREPARE,AND INSTALL DOOR LOCK.
CHECK FOR PROPER OPERATION
SET ALL FINISH NAILS AND SPACKLE AS NEEDED
P102WALLPAPER REMOVAL
P103LIGHT/HEATER/VENT INSTALLATION
TOOLS NEEDED 
PRIMARY AND ELECTRICAL TOOL BOXES /FOUR WAY SCREWDRIVER
ROTO ZIP AND TIPS /RYOBI TOOL SETUP WITH CHARGER
FOUR WAY SCREWDRIVER / ZAW-ZALL WITH  SHEETROCK BLADE
YELLOW PIG TAIL ELECTRICAL TESTER / SCREW GUN / LOADED POUCH
SAFETY EQUIPMENT / 
MATERIALS NEEDED
LIGHT/HEATER/VENT UNIT  / WIRE NUTS / ELECTRICAL TAPE / 
LIGHT SWITCH WITH BOX / ROMEX
PROCEDURE
BRING ALL ITEMS AND TOOLS NEED AS NOTED ABOVE.
STRAP ON POUCH, CUT CEILING AND INSTALL UNIT. 
MAKE ALL CONNECTIONS TO THE UNIT, 
RUN THE ROMEX TO GET ELECTRICAL POWER
TEST UNIT AND INSTALL ALL TRIMMINGS